Progress update on Chicago street corridor improvements

Webp jyx1ebv6m1bfosmcvm6qebhur0jo

Terry D'Arcy Mayor | City of Joliet

Terry D'Arcy Mayor | City of Joliet

ComEd has finished its work on vault reconstructions between Clinton and Cass Streets as part of the ongoing Chicago Street Corridor project. Additionally, landscaping to restore recent electrical installations at the Library is now complete. The intersection of Clinton and Chicago Street has been reconstructed with concrete pavement, and pedestrian crosswalks at this intersection remain accessible in all directions.

In the coming week, several tasks are scheduled for completion. These include pouring the structures for a gathering area and water feature at the north end of the park, continuing electrical work for lighting systems, and laying the concrete base for brick paver areas along Chicago Street north of Clinton. Final paving surfaces will also be placed on Clinton Street and Chicago Street north of Cass.

To facilitate proper curing of newly laid concrete, Clinton Street between Scott Street and Ottawa Street will stay closed to through traffic. Daytime parking restrictions are in place on Chicago Street between Jefferson Street and Clinton from 6 AM to 6 PM due to construction activities. Parking alternatives are available in nearby Scott Street or Ottawa Street parking garages.

Construction continues with electrical, plumbing, and framing operations focused on the northernmost water feature structure.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS