Will County Stormwater Management Planning Committee met Aug. 2.
Here are the minutes provided by the committee:
I. CALL TO ORDER / ROLL CALL
No quorum was declared.
Municipal Representative, District 3 Jonathan Dykstra called the meeting to order at 10:00 AM
Attendee Name | Title | Status | Arrived |
Robert Howard | County Representative, District 1 | Present | |
DJ Kruzel | Municipal Representative, District 1 | Absent | |
Jim Moustis | County Representative, District 2 | Absent | |
Jonathan Dykstra | Municipal Representative, District 3 | Present | |
Thomas Pawlowicz | Municipal Representative, District 4 | Present | |
Randall Jessen | Municipal Representative, District 5 | Present | |
Paul Buss | County Representative, District 6 | Absent | |
Ed Dolezal | Municipal Representative, District 6 | Present | |
Norm Likar | County Representative, District 9 | Absent | |
Ken Carroll | Municipal Representative, District 9 | Absent | |
Joe Hadamik | County Representative, District 10 | Absent | |
Theresa O'Grady | County Representative, District 11 | Absent | |
Raymund Fano | Municipal Representative, District 11 | Excused | |
Tom Weigel | County Representative, District 12 | Present | |
Will Nash | Municipal Representative, District 12 | Present | |
Bill Lamb | Municipal Representative, District 13 | Absent |
Roll Call Vote was taken. Seven Representatives were present.
II. PLEDGE OF ALLEGIANCE
Jonathan Dykstra led Pledge of Allegiance to the Flag.
III. INTRODUCTIONS
Committee Members and Land Use Staff introduce themselves.
IV. PUBLIC COMMENT
None.
V. APPROVAL OF MINUTES
No quorum, Minutes will be brought to next meeting.
1. Stormwater Management Planning Committee - Regular Meeting - Jun 7, 2022 10:00 AM
VI. NEW BUSINESS CORRESPONDENCE
1. Rock Creek Watershed Based Plan
Scott Killinger Presented the case.
Resolution 22-07: Resolution funding of the application fee required for IEPA Section 319(h) Grant for the Rock Creek Watershed Based Plan Resolution 22-08: Resolution in Support of the Rock Creek Watershed Based Plan and partial funding of the local match required for IEPA Section 319(h) Grant
22-07 Will County Rock Creek Watershed based Plan application fee $ 1,250
22-08 Will County (FY 2023) Rock Creek Watershed Plan local match and support $ 28,600
2 resolutions, sign at next meeting.
2. FMF Water Shed Plan
Scott Killinger Presented the case.
Lockport prepared a plan, the County Board to adopt the plan, by new resolution. EPA Approves 1st then other agencies Approve.
Scott Killinger: It is not ready yet, but at some point, we will look at it here and pass a resolution to adopt the plan. In the near future.
3. 2022 Project Program Discussion
Scott Killinger Presented the case.
On the consent agenda:
22-05 New Lenox Township Walona Meadows and New Lenox Heights $ 9,000 22-06 New Lenox Township Edison Industrial and Cedar Industrial Subdivisions $ 11,000
4. Will County Comeback
Scott Killinger Presented the case.
American Rescue Money
I have requested 2 million dollars of American rescue plan money for the US Army Corps of Engineers Project. That would be enough for the county to complete their obligation to the US Army Corps of Engineers. We could just pay it and then continue to move on with that.
Lockport Project: Storm sewer and ditch regrading.
The VIllage of Plainfield: Prairie Ponds Outlet.
The Village of Bolingbrook: BriarCliff Storm Sewers.
5. Consent Agenda
Scott Killinger presented.
Consent agenda
Two resolutions for New Lenox Township. Two resolutions for the rock Creek Watershed. Invoice for the lower Des Plaines Water shed group on there.
1. 12411 : 2022 Payment Approvals
No quorum, will bring back to next Meeting for Approval.
VII. REPORT OF OFFICERS, SUBCOMMITTEES, STATE'S ATTORNEY AND/OR STAFF US Army Corps of Engineers, The Du Page River project. The Plainfield township There are 3 buyout's and 3 dry flood proofing. We have met with all the residences. Appraisers is out and working on the total takes. Until I have the appraisals I have to wait. US Army Corps of Engineer is in the process of engaging a consulting engineer to evaluate at the dry flood proofing properties for that part of the work. Maybe by September or October. It is not idle.
VIII. ANNOUNCEMENTS/COMMITTEE COMMENTS
IX. ADJOURNMENT
Tom Weigel made a Motion to adjourn. William Nash seconded.
A. Next Stormwater Management Planning Committee Meeting will be held on October 4, 2022
MOTION TO ADJOURN
Voice Vote was taken, Motion to Adjourn passed, 7-0.
RESULT: APPROVED [UNANIMOUS]
MOVER: Tom Weigel, County Representative, District 12 SECONDER: Will Nash, Municipal Representative, District 12 AYES: Howard, Dykstra, Pawlowicz, Jessen, Dolezal, Weigel, Nash ABSENT: Kruzel, Moustis, Buss, Likar, Carroll, Hadamik, O'Grady, Fano, Lamb |
https://willcountyil.iqm2.com/Citizens/FileOpen.aspx?Type=12&ID=4384&Inline=True