City of Lockport issued the following announcement on Nov. 28.
11/28/2018:
D Construction recently completed installation of the parking bays and started installing piers, planters, and structural soil. The electricians have completed installation of conduit on the 900 block of State Street. Progress since Wednesday, 11/21 has been minimal due to holiday restrictions and the storm/blizzard we experienced.
Tomorrow, D Construction will complete installation of structural soil and pour the concrete piers. Planter box framing and installation will continue through the end of the week. The electricians will continue to pull conduit to its endpoint at the southwest corner of 10th/State (controller box location). Miscellaneous storm and grading work will also commence to prepare for final sidewalk installation.
11/21/2018:
As of Monday, 11/19, all water services have been transferred to the new watermain and the old State Street watermain has been retired. D construction has also paved the parking bay on the east side of the 800 and 900 blocks of State Street.
Original source can be found here.